Read Project Analytics and Team Pulse

Read progress, schedule, workload, financial and collaboration signals, then turn them into concrete project actions.

01

Delivery health has more than one dimension

Project Analytics combines progress, sprint history, task timing, specialist workload and, when enabled by the operating model, hours and commercial data. Team Pulse adds collaboration evidence that status fields alone cannot express.

The purpose is not to produce one reassuring score. Use the panels together to locate the task, sprint, specialist or collaboration pattern that needs attention.

C
Project AnalyticsDelivery and collaboration
Live
Project progress68%
Tasks complete14 / 21
Team PulseWarm · 8
Schedule risk2 tasks
Delivery timeline3 sprints · Jul 1–Aug 11
JUL 1JUL 15JUL 29AUG 11
Discovery
Prototype
Launch
Specialist workloadPlanned distribution
Strategy72%
Design88%
Delivery56%
Design is close to capacity
Delivery and collaboration evidence are read together.
02

Know what each view answers

SignalQuestion it answersUseful action
Project progressHow much planned work is complete?Open the incomplete or overdue tasks behind the percentage
Sprint timelineWhere is delivery accelerating or slipping?Inspect the sprint and its dependent tasks
Task detailsWhich task creates the signal?Open the task, owner, dates, status and Work Graph
Specialist workloadIs work concentrated or unbalanced?Reassign work or confirm realistic availability
Hours and costIs tracked delivery following the operating model?Review allocation, rate or invoice implications
Team PulseHow does collaboration around the work feel?Look for repeated tension, not a single isolated response
03

Read patterns before reacting

  1. 1
    Start with the project scope

    Confirm the selected project, planning period and operating model so the numbers have the right boundary.

  2. 2
    Compare progress with time

    A high completion rate late in the sprint is different from the same rate near the start.

  3. 3
    Open the underlying task

    Use task detail to verify status, owner, dates, dependencies and collaboration evidence.

  4. 4
    Check workload distribution

    A project can be on schedule while one specialist carries unsustainable concentration.

  5. 5
    Compare Pulse with delivery

    Warm collaboration with slipping delivery suggests a planning problem; tension with on-time delivery may signal hidden sustainability risk.

  6. 6
    Make one accountable change

    Update the task, owner, dependency, date or team conversation, then observe the next real signal.

04

Use Team Pulse as collaboration evidence

  • Pulse belongs to the work context where the experience occurred; it is not a public rating of a person.
  • A single check-in is weak evidence. Read the score together with its response count and recency.
  • Repeated cold or tense signals should trigger a calm conversation about blockers, clarity, workload or handoffs.
  • Warm signals across assessed tasks can confirm a healthy collaboration pattern, but they do not replace delivery quality.
  • Private Pulse detail remains inside the authorized project boundary; team-level views use prepared summaries.
05

Examples of useful interpretation

What you seePossible meaningWhat to do next
Many tasks in progress, few doneWork is fragmented or acceptance criteria are unclearReduce parallel work and review task outcomes
One specialist owns most planned hoursWorkload and continuity risk are concentratedRebalance or add a second owner before delay appears
Repeated blocked tasks across sprintsThe dependency model or handoff is failingOpen Work Graph and change the sequence or ownership
On-time delivery with colder PulseThe team may be absorbing hidden coordination costDiscuss workload, clarity and decision latency
Warm Pulse with overdue workThe issue may be scope, estimates or external dependency rather than conflictReview dates, scope and blockers
Cost or hours rise faster than progressThe current plan may be inefficient or under-scopedInspect the responsible tasks before changing the project budget
06

How Team Pulse is summarized